Casting and Forging
Click once on image to enlarge
The flow of the wax casting from the inquiry to clear the product
might look as follows
-
-
1. We check the drawing together with
the customers. If there are any
tolerances or other significant
dimensions, we make a note that on the
drawing or in the attached document
-
-
2. We go through the drawing with
the plant and explains the details
they need to consider.
It can be anything from tolerances-
to processing required for casting.
-
-
 3. If we have samples or
"prototypes" we complement these
to the factory. We often visit the
factories before serial production
starts to ensure quality and timetable.
-
-
4. The factory is asked to produces a
sample to verify the material and test
processing. A test piece is saved
to ensure the origin
of the material. The sample is stored for
several years with a batch number

 
5. The test takes about 3-8 weeks
depending on the size, processing
and tolerances.
We make a measurement protocol
and use an external measurement
company if necessary.
 
6.After the customer confirmed approval
test results, mass production can begin.
Delivery time is between 12-16 weeks.
 
7. Delivery will be made after
GS Materials AB has checked the details
and made a measure protocol.
We can offer customer inventory stocking,
to customers if needed.
 

.

 
 
 
 
 